What Is a Schedule of Rates? NHF/M3NHF SoR Pricing, Decoded

What a schedule of rates is, how the NHF/M3NHF SoR prices housing repairs item by item, how the tender percentage works, and where the margin sits for a sub.

Mohamed El HadriMohamed El HadriCo-Founder6 Nov 202611 min read
A repairs contractor at his van on a council estate at dusk, checking a printed rate schedule and a tablet beside a new wash hand basin still in its box

A schedule of rates is a price list agreed before any work exists: every task the client expects to order has a code, a written specification, a unit and a fixed rate, and each job is paid by code and quantity instead of by quote. In UK social housing the schedule almost everyone means is the NHF Schedule of Rates, published by M3 Housing and usually shortened to the M3NHF SoR. The V7.2 data we hold prices 3,440 separate items across 20 trades.

If you want repairs work from housing associations and councils - directly, or as a sub to the contractor who holds the contract - this is the price language you will be paid in. Most pages that rank for this term are written by the people who sell the schedule or the software that runs it. This one is written from the other side of the table: what it means for your margin when the price was set before you saw the job.

What a schedule of rates actually is

Think of it as a menu with the prices printed in advance. A landlord with 10,000 homes raises thousands of repair orders a year. Getting a quote for each one would take longer than the repairs. So the landlord agrees a single priced library up front, and from then on an order is just a code and a quantity.

Every line in the NHF schedule carries the same six things:

FieldWhat it holdsExample from V7.2
CodeA six-digit item number631501
Short descriptionThe task in capitalsSEALANT:RENEW TO SIDES AND ENDS OF BATH
Full specificationExactly what the rate includesRenew silicone sealant to side and ends of bath, providing a watertight joint
PriorityE, U, R or XR
UnitHow it is measuredIT (per item)
RateThe base price£8.87

The specification is the part people skip and should not. The rate pays for everything in that paragraph and nothing outside it. If the paragraph says "remove waste and debris", your skip is in the rate. If it says "measured separately", it is not. Half the arguments on SoR contracts are about whether something sat inside a description or outside it.

What is in the NHF schedule

I counted the V7.2 data line by line. 3,440 items, split like this:

Trade areaItems
Carpentry and joinery773
Electrical457
Plumbing434
Painting and decorating254
Brickwork196
Roofing179
Groundworks135
Disabled adaptations and minor works127
Heating, gas appliances and installations123
Fencing and gates122
Specialist treatments100
Cleaning and clearance99
Wall and floor tile and sheet finishes91
Plasterwork and other finishes85
Glazing79
Energy efficiency appliances and components77
Drainage60
Masonry21
Foundations19
Fire stopping9

Three things in that data are worth knowing before you price against it.

Most items are small. The median rate is £54.29. The range runs from 18p to £3,170.98, but the bulk of a repairs contract is a long tail of £10 to £200 jobs. That is why the percentage matters so much: you are not winning or losing on one big item, you are winning or losing on a thousand small ones.

The unit decides how you get paid. 1,523 items are priced per number (NO), 881 per item (IT), 534 per square metre (SM) and 467 per linear metre (LM). A handful run per pair, per hour, per week or per cubic metre. Skirting is per metre (£22.04 to renew softwood), a mortice lock is per number (£40.75), a basin is per number complete with taps (£200.28). Read the unit before you read the rate - a per-metre rate on a job measured wrong is the quickest way to work for free.

Every item carries a priority letter. 2,591 items are coded R, 501 U, 70 E and 278 X. E, U and R line up with the emergency, urgent and routine response bands landlords run their repairs on; the schedule's own preambles define each code, and your contract sets the actual response times. Clearing a blocked basin is an E item at £13.97. If your contract wants an E attended within hours, that £13.97 has to cover a van on standby, not just ten minutes with a plunger.

How the percentage adjustment works

This is the part that turns a price list into a tender. The landlord does not ask you to price 3,440 items. It asks for one figure: a percentage above or below the schedule's base rates. Every order for the life of the contract is then paid at base rate adjusted by your percentage.

Real examples from published tender documents:

  • A v8 housing contract fixed the adjustment at plus 12 percent for responsive repairs and minor works and plus 10 percent for void refurbishment.
  • A version 7 tender asked bidders for a single percentage adjustment, with rates deemed to include all preliminaries, overheads and profit.
  • One v8 price framework weighted the percentage adjustment at 20 percent of the price score, with access costs priced separately.

That middle line is the one to underline. Your percentage is not your profit on top of costs. Your percentage, applied to rates that already claim to include overheads, is your entire commercial position. Bid minus 5 percent and you are telling the landlord you can do every item cheaper than the book, prelims and all.

There is no published "normal" percentage, and anyone who quotes you one is guessing. It depends on region, property type, the void-to-responsive mix, travel, and whether the landlord's version of the schedule has been indexed since it was issued. The only honest way to set it is to cost a sample of the items you will actually be ordered against your real labour and materials.

A worked example: one small void job

Here is a plausible order on a void property, priced from V7.2 base rates:

ItemCodeUnitQtyBase rateLine
Renew basin on brackets, complete with taps630701NO1£200.28£200.28
Renew sealant to bath631501IT1£8.87£8.87
Renew mortice lock390903NO1£40.75£40.75
Renew softwood skirting381001LM3£22.04£66.12
Repair cracks around frame415001LM5£6.21£31.05
Base total£347.07

Now run that order through different percentages:

  • At plus 12 percent, the contractor holding the contract is paid £388.72.
  • At minus 5 percent, the same work pays £329.72.

That is a £59 swing on one small job, decided once at tender and then repeated on every order for years.

Now the subcontracting layer, which is where I live. Say the contract holder is paid at plus 12 percent and passes the plumbing, joinery and plastering to a sub at the schedule minus 10 percent. The sub is paid £312.36. The contract holder keeps £76.36, about 19.6 percent of what it was paid, for managing the order, the landlord and the paperwork. Those figures are an illustration, not a quote from any contract - but the structure is exactly how a lot of repairs work moves down the chain.

That is why I tell anyone pricing as a sub: know your cost per item, not just your day rate. If your real cost on that basin is £170 and you are paid schedule minus 10 percent (£180.25), you have £10 of margin on a job that can go wrong a dozen ways. If your cost is £120, that same item is one of the good ones. How to price jobs when you are subbing the work out walks through building that cost base.

Schedule of rates vs quoted works

A schedule of rates and a quote put the risk in different places.

Schedule of ratesQuoted works
When the price is setBefore the job existsAfter you have seen the job
Who carries the pricing riskYou, averaged across every orderYou, on this one job
How you make moneyVolume and an item mix that suits youPricing each job correctly
Admin per jobLow - code and quantityHigh - survey and quote
Where it is usedResponsive repairs, voids, planned maintenanceOne-off works, items outside the schedule

Every SoR contract has edges. Work that has no matching item is usually priced as a quotation, at an agreed day rate, or as a "star rate" built up from labour and materials. Those edges matter: a contract where half the orders end up as quotations behaves nothing like the percentage you tendered.

Where you meet a schedule of rates

Housing association and council repairs contracts. Responsive repairs, voids and minor works contracts are the natural home of the SoR, and the most common way you will see one is in the price section of a tender pack. If you have not bid for one before, the PQQ and selection questionnaire comes first - the SoR percentage is only opened once you are through it.

Council DLOs. In-house repair teams use the same schedules and subcontract the overflow. I covered how that works in how council DLOs subcontract too.

Insurance repair. Insurers and their repair networks run on their own rate schedules rather than the NHF one, but the mechanics are identical: fixed rates, set in advance, and a spread that has to survive them. Inside the insurance repair machine maps that chain.

As a sub to whoever holds the contract. This is the route most small firms actually take. You never see the landlord's tender. You see a rate card from a contractor that says "SoR minus x". Being able to read that card - and to say which items you will take and which you will not - puts you ahead of the subs who only talk day rates.

How to read a schedule before you agree to a percentage

  1. Get the version. V7 and v8 rates are not the same, and a landlord may have indexed its rates since issue. Ask which version and whether any uplift applies.
  2. Pull your top 30 items. Find the codes that will make up most of your orders in your trade. On a plumbing package that is taps, basins, WCs, sealant, blockages and leaks, not the full 434 plumbing lines.
  3. Cost each one honestly. Labour time including travel and access, materials at your real buying price, waste and disposal if the description includes it.
  4. Compare against base rate. The gap item by item tells you the percentage you can live with. If the items you will be ordered most are all under water at the proposed percentage, the contract is a loss no matter how many orders it brings.
  5. Read the preambles. The schedule's trade preambles and the contract's measurement rules decide what is inside a rate. That is where the arguments are won.

A schedule of rates does not tell you whether a job pays. It tells you what you will be paid. Whether it pays is your cost base, and only you know that.

Where this sits in the bigger picture

The SoR is the price end of the work-winning process: you get through the gates to be allowed to bid, then the schedule decides what every job is worth. The model I run - win the work, sub the delivery, keep the spread - is laid out in what construction arbitrage is, and the margin maths behind it is in construction arbitrage profit margins.

If a tender pack throws other terms at you - framework, dynamic market, approved list, social value - the plain-English glossary of construction procurement terms explains each one in a paragraph.

A note on the numbers: the item counts, units, priority codes and rates above are computed from the NHF Schedule of Rates V7.2 data we hold. They are base rates before any tendered adjustment, and v8 (revised 2023) and individual landlords' indexed versions will differ. The schedule is licensed to landlords by M3 Housing, so check prices against your contract's own version. The percentage examples are taken from published tender documents for named contracts and are not a market average.

Last checked: 6 November 2026.

Frequently asked questions

What is a schedule of rates?+

A schedule of rates is a price list agreed before any work is ordered. Every task the client expects to need - renew a basin, refix a hanging tile, replace a mortice lock - has a code, a written specification, a unit of measurement and a fixed rate. When a job comes in, the client orders it by code and quantity and the price follows automatically, so nobody has to quote. In UK social housing the most widely used one is the NHF Schedule of Rates, published by M3 Housing and often called the M3NHF SoR.

What is the NHF Schedule of Rates?+

It is a standard library of priced repair and maintenance items for social housing, produced for the National Housing Maintenance Forum and published by M3 Housing. Its developer, Rand Associates, says it is used by over 450 social landlords to procure maintenance on more than two million homes. Version 7 was revised in January 2016 and version 8 in 2023. The V7.2 data we hold contains 3,440 priced items across 20 trade areas, from groundworks to electrical.

How does the percentage adjustment on a schedule of rates work?+

The landlord does not ask you to price thousands of items. It asks for one number: a percentage plus or minus the schedule's base rates, and every order is then paid at base rate adjusted by that percentage. One v8 housing contract we read fixed it at plus 12 percent for responsive repairs and minor works and plus 10 percent for voids. The tendered rates are normally deemed to include preliminaries, overheads and profit, so the percentage is your whole margin decision in a single figure.

What is the difference between a schedule of rates and a quoted job?+

On a quoted job you price the specific work in front of you, and the risk of getting it wrong is yours once, on that job. On a schedule of rates the price was fixed before the job existed, so you carry the risk across hundreds of orders: some items will pay well, some will lose money, and you only find out which by tracking actual cost against rate. Work outside the schedule is usually priced as a quotation or at agreed day rates.

Can a small subcontractor work on a schedule of rates?+

Yes, and most do so without ever signing with the landlord. The contractor that holds the repairs contract is paid on the SoR and then subcontracts trades, often at the same schedule minus a percentage. That makes the SoR the price language of the whole chain. A sub who can read the codes, cost their own labour against them and say which items they will and will not take is far easier to put on a job than one who only quotes day rates.

Mohamed El Hadri

Mohamed El HadriCo-Founder

I'm a co-founder of several construction companies. I built a construction business from a 30-van operation into a lean model with 1,500+ subcontractors in the database - winning the work as the main contractor, subbing it out, and running it as a system from a laptop across multiple countries. I write this site from what actually works.

@mointhemarket · 35.1k followers on Instagram →
Join the players · now live

Run the model with people who already do

Reading the method is step one. Inside Construction Arbitrage Players you connect with players from around the world who run construction arbitrage every day and make real money from it - share your deals, get answers, and get in the game. Founding-member access is open now.

For the operator life and the inside story, see Contractor Club.

THE EDGE - the listening book on how the money really moves through a contracting business - is out now. Listen free, or see what is inside.

The Family Secret - how construction arbitrage really works - is coming soon.

Thinking about the exit?

A construction business built this way is a sellable asset

Systems, subs and margin - that is exactly what buyers pay for. If you own a construction or trade business and the exit is on your mind, list it on ContractorExit, the marketplace for buying and selling trade businesses. The valuation is free, so you find out what it is worth before you decide anything.

Get the Construction Arbitrage playbook

One sharp email a week: real numbers, live deal breakdowns, and the systems that let you run jobs you never visit. No fluff, unsubscribe anytime.